MyStatusFlow Docs

Subtasks

Build hierarchies in Plan Builder. Indent to create children, outdent to lift.

What are subtasks?

  • hierarchy: Child tasks nested under a parent to structure work
  • roll‑ups: Parents aggregate dates and progress from their children
  • flexible links: Subtasks can have predecessors like any task

Levels and limits

  • level 0: Top‑level tasks (no parent)
  • level 1+: Children at increasing indent levels
  • max depth: 6 levels

Creating subtasks

  • toolbar: Select a parent → Add dropdown → Subtask (or press S)
  • indent: Select a row and press Tab to make it a child of the previous non‑milestone row
  • fallbacks:
    • No selection: creates a top‑level task
    • Selected parent is a milestone: creates a top‑level task (milestones cannot be parents)
    • Insert position: placed after all of the parent’s existing children

Indent and outdent

  • indent: Moves the row (and its contiguous children) under the previous valid row; new level = min(prev.level + 1, 6)
  • outdent: Lifts the row one level; its actual children follow, preserving relative depth
  • milestones:
    • Cannot become parents; indent uses the previous non‑milestone as parent
    • Outdent avoids creating milestone parents; if it would, the outdent is skipped for that row

Scheduling and roll‑ups

  • dates: Parents roll up from children earliest child start, latest child finish, duration = business‑day span
  • progress: Parents compute percent complete from immediate non‑milestone children
  • business hours: Edits normalize to working‑day times; weekends are skipped
  • critical path: Subtasks participate in CPM like any task

Tips

  • Keep depth to 2–3 levels for readability
  • Use parents to represent phases; children for actionable work
  • Avoid adding children to milestones use a regular task instead

FAQs

Why can’t I add a subtask to this row?

It’s a milestone. Milestones can’t have children.

Why don’t parent dates match what I typed?

Parents roll up dates from children. Edit child dates to change the parent.

How do I move a subtask to a different parent?

Use Indent/Outdent (Tab/Shift+Tab) or reorder, then re‑indent.


Last updated: 2025‑10‑24